Pakistan Ramps Up Nuclear Power to Boost Low-Carbon Electric Power

Construction of 1,100 MW nuclear power reactor K2 unit in Karachi has been completed by China National Nuclear Corporation, according to media reports. A similar reactor unit K3 will add another 1,100 MW of nuclear power to the grid, bringing the total nuclear power installed capacity of Pakistan to 3,630 MW (12% of total power) by 2022.  Hualong One reactors being installed in Pakistan are based on improved Westinghouse AP1000 design which is far safer than Chernobyl and Fukushima plants.  In addition, Pakistan is also generating  9,389  MW (about 28% of total power) of low-carbon hydroelectric power in response to rising concerns about climate change.

Karachi Nuclear Power Plant (KANUPP):

With the placement of the outer containment shell, K2 is  now ready for containment and heat tests. It is scheduled to begin operations in 2020. It’s built using the Chinese HPR1000 technology, which features a dual containment design, with the outer containment providing additional protection for the primary containment.

Karachi Nuclear Power Plant K2 Unit Under Construction. Source: CNNC


KANUPP is Pakistan's first nuclear power plant where construction started in 1966 in Karachi. The plant was connected to the national grid on 18 October 1972. KANUPP, a pressurized heavy water reactor of 137 MW gross capacity was constructed by Canadian General Electric under a turnkey contract. In 1976, vendor support for spare parts and fuel was withdrawn. The PAEC undertook the task of indigenously manufacturing the required spare parts and nuclear fuel on an emergency basis and, since 1980, KANUPP has successfully operated using fuel manufactured by the PAEC, according to International Atomic Energy Agency (IAEA). Here is an except of IAEA's 2018 report on nuclear power in Pakistan:

"Despite the keen interest of Pakistan in building additional nuclear plants, it took more than two decades before the second nuclear power plant started construction. This delay was due to Pakistan’s lack of access to international nuclear technology coupled with a lack of indigenous industrial infrastructure. The construction of Pakistan’s second nuclear plant, C-1, a pressurized water reactor (PWR), was made possible in 1993 with the help of the China National Nuclear Corporation (CNNC). The plant was connected to the national grid on 13 June 2000 and has a gross capacity of 325 MW. A third nuclear power plant, C-2, with 325 MW gross capacity started commercial operation on 18 May 2011. The fourth unit, C-3, started commercial operation on 6 December 2016. It has a gross capacity of 340 MW and a similar plant, C-4, sited beside C-3, was connected to the grid on 25 June 2017. The first concrete pours to mark the start of construction of Karachi Coastal Power Project, a project containing two nuclear units, K-2 and K-3 (1100 MW each), based on an improved PWR design, were 20 August 2015 and 31 May 2016, respectively."

Pakistan Power Generation Fuel Mix. Source: Third Pole



International Energy Agency:

International Energy Agency (IEA) has recently warned that "steep decline in nuclear power would threaten energy security and climate goals". "With nuclear power facing an uncertain future in many countries, the world risks a steep decline in its use in advanced economies that could result in billions of tonnes of additional carbon emissions", the IEA has said.

Pakistan Among 31 Countries Operating Nuclear Power Plants


Nuclear is the second-largest low-carbon power source in the world today, accounting for 10% of global electricity generation. It is second only to hydropower at 16%, according to International Energy Agency (IEA). Pakistan nuclear plants are expected to generate 3,630 MW  (12% of total power vs 10% global average) by 2022.  Pakistan is also generating  9,389  MW (about 28% of total power vs 16% global average) of low-carbon hydroelectric power in response to rising concerns about climate change.

Nuclear Plant Safety Concerns:

Activists in Pakistan have raised serious concerns about potential risks from K2 and K3 plants to the population in Karachi. Are such concerns valid?

The worst nuclear disaster in the history of nuclear power generation was at Chernobyl in present day Ukraine. One of the key reasons was that the Chernobyl plant did not have the fortified containment structure common to most nuclear power plants elsewhere in the world. KANUPP K-2 and K-3 reactors have two containment shells: primary and secondary. It is noteworthy that Bhopal Union Carbide disaster was history's worst industrial disaster, far bigger in terms of human toll than the Chernobyl disaster.

China signed a technology transfer deal with the United States in 2006 that put the Westinghouse AP1000 reactor design at the “core” of its atomic energy program. Chinese reactor manufacturers also resolved to build advanced third-generation technology in their safety review after the 2011 Fukushima nuclear plant disaster.

Unlike Fukushima where underground emergency cooling system failed due to flooding, the Hualong One design stores water above the reactor that can be gravity-fed to keep it cool if the pumps fail in the event of meltdown. The Chinese HPR1000 reactors employ multiple redundant generators and cooling systems to lower meltdown risk.

Hydropower Generation:

The biggest and most important source of low-carbon energy in Pakistan is its hydroelectric power plants. Pakistan ranked third in the world by adding nearly 2,500 MW of hydropower in 2018, according to Hydropower Status Report 2019.  China added the most capacity with the installation of 8,540 megawatts, followed by Brazil (3,866 MW), Pakistan (2,487 MW), Turkey (1,085 MW), Angola (668 MW), Tajikistan (605 MW), Ecuador (556 MW), India (535 MW), Norway (419 MW) and Canada (401 MW).

New Installed Hydroelectric Power Capacity in 2018. Source: Hydrowo...

Pakistan's Water and Power Development Authority (WAPDA) says commissioning of the 108-MW Golen Gol 2, 1,410-MW Tarbela 4th Extension and 969-MW Neelum Jhelum hydropower projects in 2018 boosted its hydroelectric generating capacity of 9,389 MW, an increase of 36% in just one year, according to Hydro Review. Hydropower now makes up about 28% of the total installed capacity of 33,836 MW as of February, 2019.   WAPDA reports contributing 25.63 billion units of hydroelectricity to the national grid during the year, “despite the fact that water flows in 2018 remained historically low.” This contribution “greatly helped the country in meeting electricity needs and lowering the electricity tariff for the consumers.”

Top 20 Countries by Newly Installed Hydropower Capacity. Source: IHA

Pakistan has the potential to generate 59,000 MW of hydropower, according to studies conducted by the nation's Water and Power Development Authority (WAPDA). Currently, it's generating only 9,389 MW of hydroelectric power, about 16% of the estimated potential. Media reports indicate that China is prepared to finance and build another 40,000MW capacity as part of the development of the Northern Indus Cascade region which begins in Skardu in Gilgit-Baltistan and runs through to Tarbela, the site of Pakistan’s biggest dam, in Khyber-Pakhtunkhwa province.
Pakistan has made only a small contribution to climate change through carbon emissions.  And yet, it counts among the dozen or so nations considered most vulnerable to its damaging effects. These include rising temperatures, recurring cycles of floods and droughts and resulting disruption in food production.

Summary: 

Construction of 1,100 MW nuclear power reactor K2 unit in Karachi has been completed by China National Nuclear Corporation, according to media reports. A similar reactor unit K3 will add another 1,100 MW of nuclear power to the grid, bringing the total nuclear power installed capacity of Pakistan to 3,630 MW (12% of total power) by 2022.  Hualong One reactors being installed in Pakistan are based on improved Westinghouse AP1000 design which is far safer than Chernobyl and Fukushima plants.  In addition, Pakistan is also generating  9,389  MW (about 28% of total power) of low-carbon hydroelectric power in response to rising concerns about climate change. One of the ways Pakistan can help reduce carbon emissions is by realizing its full nuclear and hydroelectric power potential by building more nuclear plants and dams. The development of the Northern Indus Cascade region to generate 40,000MW of hydropower is a significant part of this effort.

Related Links:

Haq's Musings

South Asia Investor Review

Nuclear Power in Pakistan

Recurring Cycles of Drought and Floods in Pakistan

Pakistan's Response to Climate Change

Massive Oil and Gas Discovery in Pakistan: Hype vs Reality

Renewable Energy for Pakistan

Digital BRI: China and Pakistan Building Fiber, 5G Networks

LNG Imports in Pakistan

Growing Water Scarcity in Pakistan

China-Pakistan Economic Corridor

Ownership of Appliances and Vehicles in Pakistan

CPEC Transforming Pakistan

Pakistan's $20 Billion Tourism Industry Boom

Riaz Haq's YouTube Channel

PakAlumni Social Network

Views: 1215

Comment by Riaz Haq on June 17, 2023 at 10:08am

Pakistan will add up to 10 GW of new hydropower capacity by 2030 | Enerdata

https://www.enerdata.net/publications/daily-energy-news/pakistan-wi...

In July 2022, Pakistan commissioned the 720 MW Karot hydropower plant, one of five projects on the Jhelum River (northern Pakistan), alongside the Azad Pattan plant (700 MW), the Mangla Dam (1.1 GW), the Neelum-Jehlum plant (969 MW) and the Kohala plant (1.1 GW).

----------

700MW Azad Pattan hydropower project ready for construction: Energy China - Profit by Pakistan Today

https://profit.pakistantoday.com.pk/2023/06/14/700mw-azad-pattan-hy...

Wang Huihua, Managing Director of China Energy Int’l Group’s Pakistan Branch, announced that the 700-megawatt Azad Pattan hydropower project, run by Energy China, is ready for construction after the completion of a feasibility study and land acquisition.

Wang made these remarks at the ‘Pakistan Energy Sector Landscape: Challenges & Opportunities’ conference held at NUST University, Islamabad.

He explained that the project would provide cheap, clean energy to Pakistan. “We have been developing this project for six years. We hope the government will give it more priority in the China-Pakistan Economic Corridor (CPEC) initiative to expedite financial closure,” he said.

He further stated that Energy China believed that investing in renewable energy in Pakistan was financially viable. “We are committed to setting up our long-term operation in Pakistan and investing more,” he said.

He highlighted that China Energy Engineering Corp. (Energy China) has been present in Pakistan for the past 20 years. “Energy China considers Pakistan as its favored investment destination,” he added.

Wang also pointed out some of the challenges faced by foreign investors in Pakistan, underscoring the importance of resolving them quickly to foster win-win cooperation.

Comment by Riaz Haq on June 20, 2023 at 11:16am

#Pakistan and #China sign $4.8 billion 1200 MW #nuclear #power plant deal. Work on Chashma 5 project would begin immediately. China's support will help Pakistan make the transition away from reliance on #FossilFuels . #nuclearenergy #electricity
https://www.reuters.com/business/energy/pakistan-china-sign-48-bln-...

Pakistan and China signed a $4.8 billion deal on Tuesday to build a 1,200-megawatt nuclear power plant, Prime Minister Shehbaz Sharif said, hailing the investment by a country that Pakistan views as its most dependable ally.

Work on the Chashma 5 project would begin immediately, Sharif said on state-run news channel PTV following the signing of the memorandum of understanding (MOU) between China National Nuclear Cooperation and Pakistan Atomic Energy Commission.

"Investment from China in this project to the tune of $4.8 billion sends a message loud and clear that Pakistan is a place where Chinese companies and investors continue to show their trust and faith," Sharif said.

The Chashma 5 project will be built in the central province of Punjab. China's support will help Pakistan make the transition away from reliance on fossil fuels.

Pakistan's total nuclear energy production capacity rose to 1,400 mw, when the country's sixth nuclear power plant opened two years ago. Located in the southern port city of Karachi, that 1,100 mw plant was also constructed with Chinese assistance.

Sharif, whose government is desperately struggling to stave off a balance of payments crisis, thanked the Chinese partners for offering a $100-million discount for the latest project.

It is unclear whether the new investment is part of the $65 billion that China has pledged in infrastructure building for Pakistan under its Belt and Road Initiative.

The new project was originally planned to start a couple of years ago, and Sharif expressed thanks to the Chinese side for not rescheduling costs despite the long delay. Instead, he said, the Chinese had disbursed an initial 30 billion Pakistani rupees ($104.53 million) to start the project.

Comment by Riaz Haq on June 20, 2023 at 4:23pm

Pakistan Expanding Nuclear Plant With New Hualong One Reactor

https://www.powermag.com/pakistan-expanding-nuclear-plant-with-new-...


By Darrell Proctor is a senior associate editor for POWER (@POWERmagazine).

China continues to be a world leader in exporting its nuclear power technology. Chinese officials in Pakistan on June 20 signed a memorandum of understanding (MOU) for a $4.8 billion deal with Pakistan’s nuclear energy agency for construction of a new 1,200-MW reactor at the Chashma power complex.

The new unit will be China’s Hualong One, or HPR1000, pressurized water reactor technology.

Pakistan Prime Minister Shehbaz Sharif on Tuesday said the country considers China its “most dependable ally.” Sharif, whose country is in the midst of an economic crisis and looking for outside investment in its energy sector, said construction of the Chashma 5 project, located in Punjab province, would begin immediately.

The Chashma complex has four CNP-300 reactors currently in operation, each with 325 MW of generation capacity. The units were developed by China National Nuclear Corp. (CNNC). The first unit came online in 1991; the other units entered commercial operation in 2011, 2016, and 2017, respectively.

Chashma 5 will be built by CNNC subsidiary CNNC China Zhongyuan Engineering Corp., the company said.

Chinese officials recently announced that an HPR1000 has also been proposed for construction at the Bradwell site in the UK. Britain’s Office for Nuclear Regulation and the Environment Agency said they have started a second, technical, phase of the assessment program for the HPR1000.

Chinese Investment
Sharif, speaking Tuesday on Pakistan’s state-run news channel PTV after the signing of the MOU between the Pakistan Atomic Energy Commission and Chinese officials, said, “Investment from China in this project to the tune of $4.8 billion sends a message loud and clear that Pakistan is a place where Chinese companies and investors continue to show their trust and faith.”

The prime minister originally brokered the project during his time as chief minister of Punjab, an office he held three times, most recently from 2013 to 2018. He was elected as Pakistan’s prime minister in April 2022.

Sharif has supported nuclear power as a way to move Pakistan away from fossil fuels. Its most recent nuclear facility, the 2,200-MW Karachi Nuclear Power Plant, also known as KANUPP, in the southern port city of Karachi, commissioned its two reactors in 2021 and 2022, respectively. That facility, featuring two Hualong One Generation III pressurized water reactors, also was built with financial backing from China.

Sharif on Tuesday said the Chashma 5 project was originally planned to start in 2021. He said Chinese officials did not raise the cost of the project from original estimates despite the delay. Officials on Tuesday said China has to date disbursed 30 billion Pakistani rupees ($104.53 million) to start the project.

“We are deeply obliged to [China] President Xi Jinping, and the Chinese leadership for their generous help to Pakistan,” Sharif said. He also recognized Saudi Arabia, United Arab Emirates and Qatar for extending financial support to Pakistan’s government.

Pakistan for years has contended with power outages. Two of the worst incidents occurred in January 2021, and again in January of this year. In 2021, a fault at a power plant brought down the national grid, leading to calls for a massive overhaul of the country’s electricity transmission infrastructure.

A nationwide power outage on Jan. 30 of this year impacted all of Pakistan’s major cities and left millions of people without electricity.

Comment by Riaz Haq on June 20, 2023 at 5:16pm

Pakistan Signs $4.8 Billion Nuclear Power Plant Deal With China

https://www.voanews.com/a/pakistan-signs-4-8-billion-nuclear-power-...


Pakistan and China signed a $4.8 billion deal Tuesday to build what would be the seventh Chinese nuclear power plant in the South Asian nation.

The 1,200-megawatt project will be installed in the central Pakistani city of Chashma, where Beijing already has built four nuclear power generation units with a collective output of nearly 1,230 megawatts.

Prime Minister Shehbaz Sharif oversaw Tuesday's signing of the memorandum of understanding between China National Nuclear Cooperation and the Pakistan Atomic Energy Commission.

According to the agreement, the Chinese company will employ its HPR 1000 technology, known as HPR1000 or Hualong One, to construct the nuclear power unit. It will be the third facility in Pakistan to feature the HPR 1000, or pressurized water reactor technology.

"Investment from China in this project to the tune of $4.8 billion sends a loud and clear message that Pakistan is a place where Chinese companies and investors continue to show their trust and faith," Sharif said.

He thanked Beijing for offering a more than $100 million discount for what is named the Chashma 5 power plant. The work on the project was initially planned to start a couple of years ago, but Sharif said the Chinese partners had not rescheduled costs despite the long delay.

"This project is part of our energy security plan to diversify the energy mix with a focus on ensuring the provision of cheap electricity to the industry & relief to the common man,” the Pakistani prime minister wrote on Twitter after the ceremony.

Sharif's coalition government is struggling to deal with unprecedented economic challenges facing Pakistan, including a balance of payments crisis.

China has recently also constructed two nuclear power plants in the southern port city of Karachi, each with a 1,100-megawatt generation capacity.

Pakistani officials say the two Chinese-supplied third-generation Hualong One reactors, known as K2 and K3, cost roughly $10 billion. They are equipped with "advanced safety and foolproof security features" and have enhanced Pakistan's nuclear energy production to more than 3,500 megawatts.

"K2 and K3 are fully functional and supply 2,200 megawatts of electricity to the national grid. Similarly, nuclear power plants at Chashma are contributing more than 1,300 megawatts," a PAEC spokesman told VOA on Tuesday.

Canada helped Pakistan build its first nuclear power plant in 1972 in Karachi, producing about 80 megawatts of electricity. It is expected to be shut down soon after having served its purpose for about the full extent of the planned operation.

China maintains close defense and economic relations with staunch ally Pakistan. It has invested more than $20 billion in building road networks, power plants, and ports over the past decade under what is known as the China-Pakistan Economic Corridor, or CPEC.

Officials in both countries say the collaboration, an extension of Beijing's global Belt and Road infrastructure initiative, has created tens of thousands of jobs and ended Pakistan's crippling energy crisis.

Comment by Riaz Haq on June 22, 2023 at 10:54am

Dasu Hydropower Project: Stage 1 of concrete Starter Dam completed


https://www.nation.com.pk/22-Jun-2023/dasu-hydropower-project-stage...

In a major development towards implementation of Dasu Hydropower Project, Stage 1 of the concrete Starter Dam has been completed upstream of Main Dam site.

As per the design, the Starter Dam for Dasu Hydropower Project is to be completed in two stages; Stage 1 up to elevation of 785 meters while Stage 2 up to elevation of 798 meters above mean sea level, said a spokesperson WAPDA here. The Stage 1 of the concrete Starter Dam was completed in June this year before the high flow season – a major landmark which the project team successfully achieved, the spokesperson said.

As the high flow season has started, River Indus is flowing through the two diversion tunnels completed earlier this year, while some of the river water is overtopping the concrete Starter Dam as designed.

After the high flow season in October this year, the construction of the Starter Dam’s Stage 2 will be carried out. The Stage 2 is scheduled for completion during the coming low flow season. The project is being constructed across the River Indus, upstream of Dasu Town in Upper Kohistan district of Khyber Pakhtunkhwa. The 4,320-MW-Dasu Hydropower Project is planned to be completed in two stages. At present, WAPDA is constructing its stage-I with installed generation capacity of 2,160-MW and annual energy generation of 12 billion units. Stage-I of the project is likely to start electricity generation in 2026. The 2,160-MW stage-II, when implemented, will also provide 9 billion units to the national grid. On completion of the both stages, Dasu will become the project with highest annual energy generation in Pakistan i.e. 21 billion units per annum on the average. The project will commence by end 2026. It is worth mentioning here that in February this year, Dasu Hydropower Project crossed a major milestone as the River Indus was successfully diverted following completion of a 1.33-kilometre long diversion tunnel.


Following the completion of one of the two diversion tunnels, the River Indus was successfully diverted to the completed tunnel. Instead of its natural course, the River Indus is now flowing through a 1.33-kilometer long diversion tunnel with 20-metre width and 23-metre height. Consequently, construction activities have been initiated on the starter dam, leading towards construction of the main dam of Dasu Hydropower Project.

Comment by Riaz Haq on July 14, 2023 at 7:19am

Pakistan’s PM Shehbaz Sharif launches US$3.5 billion Chinese-designed nuclear energy project

https://www.scmp.com/news/asia/south-asia/article/3227776/pakistans...

The two countries had already signed an agreement to construct a state-of-the-art Hualong One reactor
China also gave US$5 billion loan to Pakistan to help it unlock a bailout from the IMF



Pakistan’s Prime Minister Shehbaz Sharif on Friday launched the construction of a 1,200-megawatt Chinese-designed nuclear energy project, which will be built at a cost of US$3.5 billion as part of the government efforts to generate more clean energy in the Islamic nation.
The ceremony to mark the project’s start comes less than a month after Pakistan signed an agreement with China’s National Nuclear Corporation Overseas in the capital, Islamabad, to construct a Hualong One reactor – a third-generation nuclear reactor and is considered safer because of the latest security features.
Pakistan and China are long-time allies. Pakistan’s relations with Beijing are so close that its leadership calls China their “Iron Brother.” China is also building roads, bridges, power plants, and railways to link its far west with the Chinese-built port of Gwadar on the Indian Ocean.

Comment by Riaz Haq on July 14, 2023 at 12:43pm

China Begins Construction of Pakistan's Largest Nuclear Power Plant

https://www.voanews.com/a/china-begins-construction-of-pakistan-s-l...


Pakistan held a groundbreaking ceremony Friday for what will be its largest civil nuclear power plant — constructed by China — that will contribute 1,200 megawatts of electricity daily to the national grid and is estimated to cost at least $3.5 billion.

Prime Minister Shehbaz Sharif and senior Chinese officials attended the televised event in the central city of Chashma, dubbed the birthplace of China-Pakistan nuclear energy cooperation.

Over the past 30 years, Beijing has installed four nuclear power generation units in Chashma, collectively generating about 1,300 megawatts, with China providing enriched uranium for fuel.

"This mutual cooperation to promote clean, efficient, and comparatively cheaper energy is a gift of friendship between the two countries and a model for other countries to emulate," Sharif said at the ceremony.

The plant, known as Chashma-5, or C-5, will feature what China says is its domestically developed third-generation pressurized water nuclear technology, the Hualong One or HPR1000, with "advanced safety and foolproof security features."

Raja Ali Raza, the head of the Pakistan Atomic Energy Commission, said the nuclear plant project will be completed by 2030.

"C-5 will be Pakistan's largest generation-III plus nuclear power project," Raza said. "This project has brought PAEC one step closer to its envisaged goal of production of 8,800 megawatts electric cheap and clean energy."

Beijing has previously supplied the HPR1000 technology for two nuclear power stations, each with a 1,100-megawatt generation capacity, built and operationalized in the last couple of years in the southern port city of Karachi, enhancing Pakistan's nuclear energy production to more than 3,500 megawatts a day.

Analysts see China's accelerated civil nuclear cooperation with Pakistan as part of efforts to globally find more lucrative buyers for its HPR1000 reactors developed by state-owned China National Nuclear Corporation or CNNC, the country's second-largest nuclear power producer company.


"HPR1000 is a homegrown nuclear technology of CNNC and a flagship of China's advanced equipment manufacturing," Yu Jianfeng, the CNNC chairman, told the ceremony. He noted that more than 17 units of HPR1000 are currently under construction in China.

"Today's groundbreaking for the C-5 project is a significant milestone for HPR1000's global journey and a new start for the China-Pakistan nuclear energy cooperation," Yu stated. "Our cooperation in nuclear energy has become an integral part of the China-Pakistan all-weather strategic cooperative partnership and a shining example of international nuclear energy cooperation."

Under its global Belt and Road Initiative, Beijing also has built and put into commercial operation 14 mostly coal-fired power plants in Pakistan in the last 10 years, with a total installed capacity of 8,000 megawatts daily.

The projects are part of the China-Pakistan Economic Corridor, or CPEC, which has also built road networks, highways, ports, and industrial zones with direct Chinese investment and "soft loans," expected to increase to about $62 billion by 2030 when the mega undertaking is due to be complete.

Critics blame CPEC for contributing to Pakistan's deepening economic troubles and depleting foreign exchange reserves, making it difficult for the country to catch up with its foreign debt repayments.

Pakistan owes more than $1.3 billion (350 billion rupees) to Chinese power plants. The amount keeps growing, and China has refused to defer or restructure the payment and CPEC debt repayments.

Comment

You need to be a member of PakAlumni Worldwide: The Global Social Network to add comments!

Join PakAlumni Worldwide: The Global Social Network

Pre-Paid Legal


Twitter Feed

    follow me on Twitter

    Sponsored Links

    South Asia Investor Review
    Investor Information Blog

    Haq's Musings
    Riaz Haq's Current Affairs Blog

    Please Bookmark This Page!




    Blog Posts

    Pakistani Student Enrollment in US Universities Hits All Time High

    Pakistani student enrollment in America's institutions of higher learning rose 16% last year, outpacing the record 12% growth in the number of international students hosted by the country. This puts Pakistan among eight sources in the top 20 countries with the largest increases in US enrollment. India saw the biggest increase at 35%, followed by Ghana 32%, Bangladesh and…

    Continue

    Posted by Riaz Haq on April 1, 2024 at 5:00pm

    Agriculture, Caste, Religion and Happiness in South Asia

    Pakistan's agriculture sector GDP grew at a rate of 5.2% in the October-December 2023 quarter, according to the government figures. This is a rare bright spot in the overall national economy that showed just 1% growth during the quarter. Strong performance of the farm sector gives the much needed boost for about …