Pakistan Ramps Up Nuclear Power to Boost Low-Carbon Electric Power

Construction of 1,100 MW nuclear power reactor K2 unit in Karachi has been completed by China National Nuclear Corporation, according to media reports. A similar reactor unit K3 will add another 1,100 MW of nuclear power to the grid, bringing the total nuclear power installed capacity of Pakistan to 3,630 MW (12% of total power) by 2022.  Hualong One reactors being installed in Pakistan are based on improved Westinghouse AP1000 design which is far safer than Chernobyl and Fukushima plants.  In addition, Pakistan is also generating  9,389  MW (about 28% of total power) of low-carbon hydroelectric power in response to rising concerns about climate change.

Karachi Nuclear Power Plant (KANUPP):

With the placement of the outer containment shell, K2 is  now ready for containment and heat tests. It is scheduled to begin operations in 2020. It’s built using the Chinese HPR1000 technology, which features a dual containment design, with the outer containment providing additional protection for the primary containment.

Karachi Nuclear Power Plant K2 Unit Under Construction. Source: CNNC


KANUPP is Pakistan's first nuclear power plant where construction started in 1966 in Karachi. The plant was connected to the national grid on 18 October 1972. KANUPP, a pressurized heavy water reactor of 137 MW gross capacity was constructed by Canadian General Electric under a turnkey contract. In 1976, vendor support for spare parts and fuel was withdrawn. The PAEC undertook the task of indigenously manufacturing the required spare parts and nuclear fuel on an emergency basis and, since 1980, KANUPP has successfully operated using fuel manufactured by the PAEC, according to International Atomic Energy Agency (IAEA). Here is an except of IAEA's 2018 report on nuclear power in Pakistan:

"Despite the keen interest of Pakistan in building additional nuclear plants, it took more than two decades before the second nuclear power plant started construction. This delay was due to Pakistan’s lack of access to international nuclear technology coupled with a lack of indigenous industrial infrastructure. The construction of Pakistan’s second nuclear plant, C-1, a pressurized water reactor (PWR), was made possible in 1993 with the help of the China National Nuclear Corporation (CNNC). The plant was connected to the national grid on 13 June 2000 and has a gross capacity of 325 MW. A third nuclear power plant, C-2, with 325 MW gross capacity started commercial operation on 18 May 2011. The fourth unit, C-3, started commercial operation on 6 December 2016. It has a gross capacity of 340 MW and a similar plant, C-4, sited beside C-3, was connected to the grid on 25 June 2017. The first concrete pours to mark the start of construction of Karachi Coastal Power Project, a project containing two nuclear units, K-2 and K-3 (1100 MW each), based on an improved PWR design, were 20 August 2015 and 31 May 2016, respectively."

Pakistan Power Generation Fuel Mix. Source: Third Pole



International Energy Agency:

International Energy Agency (IEA) has recently warned that "steep decline in nuclear power would threaten energy security and climate goals". "With nuclear power facing an uncertain future in many countries, the world risks a steep decline in its use in advanced economies that could result in billions of tonnes of additional carbon emissions", the IEA has said.

Pakistan Among 31 Countries Operating Nuclear Power Plants


Nuclear is the second-largest low-carbon power source in the world today, accounting for 10% of global electricity generation. It is second only to hydropower at 16%, according to International Energy Agency (IEA). Pakistan nuclear plants are expected to generate 3,630 MW  (12% of total power vs 10% global average) by 2022.  Pakistan is also generating  9,389  MW (about 28% of total power vs 16% global average) of low-carbon hydroelectric power in response to rising concerns about climate change.

Nuclear Plant Safety Concerns:

Activists in Pakistan have raised serious concerns about potential risks from K2 and K3 plants to the population in Karachi. Are such concerns valid?

The worst nuclear disaster in the history of nuclear power generation was at Chernobyl in present day Ukraine. One of the key reasons was that the Chernobyl plant did not have the fortified containment structure common to most nuclear power plants elsewhere in the world. KANUPP K-2 and K-3 reactors have two containment shells: primary and secondary. It is noteworthy that Bhopal Union Carbide disaster was history's worst industrial disaster, far bigger in terms of human toll than the Chernobyl disaster.

China signed a technology transfer deal with the United States in 2006 that put the Westinghouse AP1000 reactor design at the “core” of its atomic energy program. Chinese reactor manufacturers also resolved to build advanced third-generation technology in their safety review after the 2011 Fukushima nuclear plant disaster.

Unlike Fukushima where underground emergency cooling system failed due to flooding, the Hualong One design stores water above the reactor that can be gravity-fed to keep it cool if the pumps fail in the event of meltdown. The Chinese HPR1000 reactors employ multiple redundant generators and cooling systems to lower meltdown risk.

Hydropower Generation:

The biggest and most important source of low-carbon energy in Pakistan is its hydroelectric power plants. Pakistan ranked third in the world by adding nearly 2,500 MW of hydropower in 2018, according to Hydropower Status Report 2019.  China added the most capacity with the installation of 8,540 megawatts, followed by Brazil (3,866 MW), Pakistan (2,487 MW), Turkey (1,085 MW), Angola (668 MW), Tajikistan (605 MW), Ecuador (556 MW), India (535 MW), Norway (419 MW) and Canada (401 MW).

New Installed Hydroelectric Power Capacity in 2018. Source: Hydrowo...

Pakistan's Water and Power Development Authority (WAPDA) says commissioning of the 108-MW Golen Gol 2, 1,410-MW Tarbela 4th Extension and 969-MW Neelum Jhelum hydropower projects in 2018 boosted its hydroelectric generating capacity of 9,389 MW, an increase of 36% in just one year, according to Hydro Review. Hydropower now makes up about 28% of the total installed capacity of 33,836 MW as of February, 2019.   WAPDA reports contributing 25.63 billion units of hydroelectricity to the national grid during the year, “despite the fact that water flows in 2018 remained historically low.” This contribution “greatly helped the country in meeting electricity needs and lowering the electricity tariff for the consumers.”

Top 20 Countries by Newly Installed Hydropower Capacity. Source: IHA

Pakistan has the potential to generate 59,000 MW of hydropower, according to studies conducted by the nation's Water and Power Development Authority (WAPDA). Currently, it's generating only 9,389 MW of hydroelectric power, about 16% of the estimated potential. Media reports indicate that China is prepared to finance and build another 40,000MW capacity as part of the development of the Northern Indus Cascade region which begins in Skardu in Gilgit-Baltistan and runs through to Tarbela, the site of Pakistan’s biggest dam, in Khyber-Pakhtunkhwa province.
Pakistan has made only a small contribution to climate change through carbon emissions.  And yet, it counts among the dozen or so nations considered most vulnerable to its damaging effects. These include rising temperatures, recurring cycles of floods and droughts and resulting disruption in food production.

Summary: 

Construction of 1,100 MW nuclear power reactor K2 unit in Karachi has been completed by China National Nuclear Corporation, according to media reports. A similar reactor unit K3 will add another 1,100 MW of nuclear power to the grid, bringing the total nuclear power installed capacity of Pakistan to 3,630 MW (12% of total power) by 2022.  Hualong One reactors being installed in Pakistan are based on improved Westinghouse AP1000 design which is far safer than Chernobyl and Fukushima plants.  In addition, Pakistan is also generating  9,389  MW (about 28% of total power) of low-carbon hydroelectric power in response to rising concerns about climate change. One of the ways Pakistan can help reduce carbon emissions is by realizing its full nuclear and hydroelectric power potential by building more nuclear plants and dams. The development of the Northern Indus Cascade region to generate 40,000MW of hydropower is a significant part of this effort.

Related Links:

Haq's Musings

South Asia Investor Review

Nuclear Power in Pakistan

Recurring Cycles of Drought and Floods in Pakistan

Pakistan's Response to Climate Change

Massive Oil and Gas Discovery in Pakistan: Hype vs Reality

Renewable Energy for Pakistan

Digital BRI: China and Pakistan Building Fiber, 5G Networks

LNG Imports in Pakistan

Growing Water Scarcity in Pakistan

China-Pakistan Economic Corridor

Ownership of Appliances and Vehicles in Pakistan

CPEC Transforming Pakistan

Pakistan's $20 Billion Tourism Industry Boom

Riaz Haq's YouTube Channel

PakAlumni Social Network

Views: 1215

Comment by Riaz Haq on March 16, 2022 at 12:47pm

Fitch Affirms Pakistan Water and Power Development Authority at 'B-'; Outlook Stable


https://www.fitchratings.com/research/international-public-finance/...



WAPDA is established under a special statute. The Authority has close operational and administrative linkage to the government and is mandated to develop water and power resources in Pakistan. The government exercise strong influence over WAPDA's corporate governance and debt, sanctioned by the government, shall be transferred to the government according to the Pakistan Water and Power Development Authority Act.

KEY RATING DRIVERS
Status, Ownership and Control: 'Very Strong'


Our 'Very Strong' assessment of 'Status, Ownership and Control' remains unchanged, given the strong statutory support, stable government ownership - which we do not expect to change - and high level of government control. Employees of WAPDA are deemed to be public servants when acting in pursuance of WAPDA activities. The government has strong influence on WAPDA's corporate governance, including budget, accounts, financing activity and new power station investment plans, because the Authority is mandated to execute the government's responsibility of utilising Pakistan's water and power resources.

Support Track Record: 'Very Strong'


The build-up of circular debt in the energy sector exposes WAPDA to external funding. The government aims to mitigate the circular debt issue by providing financial support; it had guaranteed 22% of WAPDA's interest-bearing debt as of June 2021 and 56% of the debt comprises of government loans. The government will be liable for loans passed by the Authority with the sanction of the government under the WAPDA Act. Supportive policies, such as corporate tax exemptions, land acquisitions and a tariff mechanism, also enhance WAPDA's operational stability.

Socio-Political Implications of Default: 'Strong'


Pakistan's policies aim to boost the hydropower generation mix and reduce reliance on fossils. WAPDA's hydropower generation accounted for 27% of the generation mix in 2021, while other renewable energy only accounted for 3%. The government aims for hydro power to contribute over 40% of Pakistan's energy demand by 2030, implying that the development of hydropower generation is of significant strategic importance to the country. We believe WAPDA's installed capacity would be difficult to substitute and that any transition process would lead to severe service disruption.

Financial Implications of Default: 'Very Strong'


We deem WAPDA as a proxy financing vehicle for the government in the energy sector. The Authority still relies on the government to fund its investments, although it is expanding its borrowing capacity, including via recent bond issues. We believe the government's borrowing ability would be significantly impaired if WAPDA come under financial stress due to the high level of funding it receives from international development finance institutions and its debt mix - 78% of interest-bearing debt comprised loans or was guaranteed by the government.

Derivation Summary

WAPDA's ratings reflect our assessment of government linkage and support incentive and results in a weighted score of 50, based on our Government-Related Entities Rating Criteria. We adopt a top-down approach and equalise WAPDA's rating with those of Pakistan (B-/Stable), regardless of WAPDA's Standalone Credit Profile.

Comment by Riaz Haq on March 30, 2022 at 8:26pm

Nuclear power generation
By Engr. Hussain Ahmad Siddiqui Mon, 03, 22
This month is marked with Pakistan achieving milestone of 3,635-MWe cumulative nuclear power generation capacity as the third nuclear power plant at Karachi is connected to the national grid for testing, and will shortly commence commercial operations.

https://www.thenews.com.pk/magazine/money-matters/941162-nuclear-po...

his month is marked with Pakistan achieving milestone of 3,635-MWe cumulative nuclear power generation capacity as the third nuclear power plant at Karachi is connected to the national grid for testing, and will shortly commence commercial operations.

Commonly known as Kanupp-3 or K-3, it is of 1,145-MWe generation installed capacity and 1,100-MWe net capacity, which had attained criticality last month, and was undergoing safety tests and procedures. Generation cost is about Rs 9.59 per KWh (levelised). The foreign exchange portion of the project, which is about 80 percent of total cost, has been financed through a loan from the China’ state-owned The Export-Import Bank of China.

With the addition of K-3 nuclear power plant, currently there are total seven nuclear power plants installed in the country, out of which six, of cumulative installed capacity of 3,635-MWe, are in operation. The first–ever nuclear power plant constructed in the country, Kanupp-1 (K-1), has been permanently shut down. With the commencement of commercial operations of K-3, the share of nuclear energy in overall generation mix from all resources at national level has significantly increased, to over 9.1 percent. This share, which was 1.1 percent in 1990, has gradually and steadily increased in later years to 7.1 percent in 2020, before achieving the present level.

These nuclear power plants, established with technical and economic support of China, are owned and operated by the Pakistan Atomic Energy Commission (PAEC), and regulated by the Pakistan Nuclear Regulatory Authority (PNRA) under the safeguards of the International Atomic Energy Agency (IAEA). These facilities are located only at two sites — Chashma (District Mianwali) and Karachi. There are four nuclear power plants, namely Chasnupp-1 (C-1) of 325-MWe installed capacity, and plants C-2, C-3 and C-4, each of 340-MWe capacity.

These four plants at Chashma were commissioned in the years 2000, 2011, 2016 and 2017, respectively, and their corresponding operating licenses are valid until December 2030, 2026, 2026 and 2027. Pakistan has an impeccable record of safety and security in operating these nuclear power plants, as it follows best practices and standards set by the IAEA. Pakistan is currently ranked 17th out of 25 countries on Nuclear Materials Safety Index in terms of safety, and security and is placed above India.

Karachi Coastal Power Complex consists of two units of 1,145-MWe each installed capacity, known as K-2 and K-3 for which China has provided $6.5 billion loan on soft terms. The earlier unit K-2 was connected to the system of the National Transmission and Despatch Co (NTDC) in May 2021. These are third-generation nuclear power plants developed and tested by the Chinese as “Advanced China Pressurized ACP-1000”. Electricity transmission infrastructure for evacuation of power from these plants include additional 550kv and 220kv transmission lines of 16-km that have recently been completed by the NTDC at a cost of Rs5.6 billion.

The K-1nuclear power plant of 137-MWe capacity was constructed near Karachi in 1971, and connected to the national grid in October 1972. It was designed to operate for 30-years’operation. On end of its service life in 2002, the major balancing, modernization & rehabilitation (BMR) and safety upgrades of the facility were carried out by the PAEC, and it operated safely since 2003 till recently at de-rated capacity of around 98-MWe. After 50-years’ record successful operation the plant has been shut-down in August 2021 for dismantling and decommissioning.

Comment by Riaz Haq on April 20, 2022 at 7:30am

Shehbaz Sharif, the newly installed prime minister of Pakistan, has ordered the completion of the $2.8bn Diamer Bhasha Dam in Kashmir three years earlier than scheduled.

https://www.globalconstructionreview.com/new-pakistan-pm-calls-for-...

An element of the China-Pakistan Economic Corridor (CPEC), the dam is being built by a joint venture between China Power and the Frontier Works Organisation, an engineering arm of Pakistan’s army.

When work began in 2020, it was expected to finish in 2028. Sharif now wants this to happen in 2026.

He made the call during a speech delivered to the Water and Power Development Authority (WAPDA) at the site of the project on Sunday, newspaper Dawn reports.

He said the electricity and irrigation produced by the dam would help to make Pakistan “prosperous and progressive”.

Claiming to understand the difficult terrain of the area and Pakistan’s difficulties in raising funds for construction, he added: “I am sure that all of you are going to work as a team and make efforts for the biggest energy project and complete it as early as possible.”

He also urged international investors to come forward and invest in the project.

The project is to build a roller-compacted gravity dam with a barrier some 272m high, making it the tallest of its type in the world.

The reservoir will contain 10 cubic kilometres of River Indus water, and its two powerhouses are expected to generate 4.5GW of electricity, equivalent to 12% of Pakistan’s total installed capacity.

The dam is being built in mountainous terrain between Kohistan district in Khyber Pakhtunkhwa and Diamer district in Gilgit Baltistan.

According to Dawn, engineers who have completed hydropower projects in the region suggested that it was more likely that the project would take longer than nine years to complete, rather than fewer.

However, the Lahore Chamber of Commerce & Industry welcomed the expedited schedule.

Its president Mian Nauman Kabir said on Monday that the project would serve as a “lifeline” for the country by improving its energy mix, cutting its huge oil import bill and bringing down the cost of doing business.

Comment by Riaz Haq on April 21, 2022 at 12:31pm

Under the project, a 150 MW floating solar subproject will be deployed in the Ghazi Barrage headpond and another floating project of similar capacity at the Forebay of the existing Ghazi Barotha Hydropower plant. The project would greatly enhance the electricity supply and help meet the rising demand for electricity in the country.

https://www.globalvillagespace.com/world-bank-wapda-to-setup-pakist...

Currently, according to the National Electric Power Regulator Authority state industry report 2021, Pakistan’s total installed electricity generation capacity is 143,588 GWH, of which a measly 4,521 GWH is produced by renewable sources such as solar and wind. Thermal sources account for 61.76 percent, whereas Hydel sources account for 27.02 percent. A shift toward renewable sources of energy was long pending and is a major component of Pakistan’s vision 2050.

The Water and Power Development Authority (WAPDA) plans to take on the Floating Solar Project (FSP or the Project) and, in that effort, seeks financing from the World Bank. Pakistan’s Water and Power Development Authority has prepared a Stakeholder Engagement Plan (SEP), and according to a report by Business Recorder, it is engaged in meetings with the World Bank to establish a 300 MW floating solar project in the country.

A delegation from the World Bank is expected to reach Pakistan today for a ten-day visit, for the initial assessment and evaluation of the project. The World Bank delegation will meet with all the relevant authorities and stakeholders, such as the Ministry of Water Resources, Water and Power Development Authority, and the Economic Affairs Division. After the visit, the World Bank mission would generate a feasibility report of the project, which would detail the proposed financing and the expected Return on Investment (ROI) in the following period.

The World Bank team includes but is not limited to; Gunjan Gautam (Senior Energy Specialist and Task Team Leader), Rikard Liden (Lead Energy Specialist and co-Task Team Leader), Imran ul Haq (Senior Social Development Specialist), Sana Ahmad (Environmental Specialist), Uzma Sadaf (Sr Procurement Specialist), Shafiq Hussain (Procurement Specialist), Noureen LNU (Financial Management Specialist), Mohammad Omar Khalid (Senior Consultant) to be supported by Amna W Mir (Senior Program Associate).

The World Bank mission is expected to hold a meeting with the project management unit of WAPDA on the 22 April in Islamabad. Following which, it is scheduled to meet with the officials of the Water Resources Ministry on 23 April. The mission would also listen to briefings and partake in discussion sessions with the relevant authorities.
According to the initial assessment conducted by the Water and Power Distribution Authority of Pakistan, the project is expected to strengthen the capacity of WAPDA as it increases the supply of electricity by financing 300 MW floating solar subprojects in water body of the already existing project of the Ghazi-Barotha complex.

Comment by Riaz Haq on May 7, 2022 at 12:54pm

Karot Hydropower connects unit one to national grid. It is a 720 MW plant constructed on river Jhelum, #Pakistan , in collaboration with one of the largest state-owned #Chinese power companies, #China Three Gorges Corporation. #CPEC Global Village Space

https://www.globalvillagespace.com/karot-hydropower-connects-unit-o...


Pakistan’s first Hydel power generation project – Karot Hydropower – under the China-Pakistan Economic Corridor (CPEC) connected unit one to the national grid on 30 April, kick-starting the operations at full capacity, reported Developing Pakistan, a Pakistan based digital media platform. By connecting unit one of the Karot Hydropower, the project pumps 180 MW of electricity into the national grid. Karot Hydropower Project is a 720 MW constructed on river Jhelum, Pakistan, in collaboration with one of the largest state-owned Chinese power companies, the China Three Gorges Corporation, more commonly known as the CTG. The rest of the three units will be connected to the national grid in the upcoming months.

The project’s financial close was achieved in March 2017, and construction work began the same year. The mechanical, electrical, and other technical works of the project were completed around February 2022, and internal testing began in the same month. Work pertaining to transmitting power to the national grid was mostly completed by January however was not completed till April 30. The project is the first of three hydropower projects under China Pakistan Economic Corridor, and the estimated cost to get the plant operational stands at around $1.42 billion. According to the Managing Director of the Private Power and Infrastructure Board, the other two include “the 870MW Sukhi Kenari HPP and 1,124MW Kohala HPP.” Work on Sukhi Kerani is underway, whereas the construction of the Kohala Hydropower Project is yet to be initiated. The Kohala HPP is also being constructed on the Jhelum river, and a tripartite agreement was signed for its construction in June 2020; however, due to tax issues, the work on the construction site of the said river has still not begun.

It is pertinent to mention that according to the National Electric Power Regulator Authority state industry report 2021, Hydel sources of electricity generation account for 27.02 percent of the country’s electricity, significantly more than any other source except for thermal.

Separately, to address the energy demands of the country, Pakistani authorities have also engaged the World Bank to facilitate the set up of a 300 MW floating solar project at the Tarbela – Ghazi Barotha complex. The project’s projected cost is proposed to be around $346.5 million. Under the project, a 150 MW floating solar subproject will be deployed in the Ghazi Barrage headpond and another floating project of similar capacity at the Forebay of the existing Ghazi Barotha Hydropower plant. The project would greatly enhance the electricity supply and help meet the rising demand for electricity in a climate-smart manner.

Comment by Riaz Haq on August 21, 2022 at 4:16pm

The last stator frame at the (864 MW) Suki Kinari hydropower project (on the Kunhar river in the Kaghan valley of Mansehra District Khyber Pakhtunkhwa) has been hoisted successfully and lowered into the unit pit.

https://www.app.com.pk/global/last-stator-hoisted-successfully-at-c...


The stator weighed 335 tons and the task was completed with the help of bridge cranes. The project has four electricity generation units with a combined capacity of 884 megawatts.

The run-of-river facility is one of the early-harvest clean energy projects under China-Pakistan Economic Corridor (CPEC). Gezhouba Group, China is implementing the project at around $2 billion, China Economic Net (CEN) reported.

Also, the 5-kilometre-long relocated portion of National Highway 15 (N-15) is open to traffic. The existing portion of N-15 will submerge in the reservoir of the Suki Kinari hydropower project; therefore, the new road was constructed at a higher elevation. The new road also has a 411-metre-long tunnel.

The project is expected to complete by the end of 2023 or mid 2024, an official said. He said that the powerhouse and reservoir parts of the project were at advanced stages of completion. However, the 24-kilometre-long headrace tunnel is the most challenging part of the project due to unpredictable terrain, tough weather conditions during winters and dewatering issues, he said.

Gezhouba has deployed the most skilled workforce and state-of-the-art machinery at the tunnel sites and presently excavation and lining works are underway from both upstream and downstream sides, he said.

The project will add around 3 billion units of cheap electricity into the national grid annually after completion.

Comment by Riaz Haq on November 9, 2022 at 2:32pm

Unit 3 of the Karachi nuclear power plant in Pakistan - a Chinese-supplied Hualong One reactor - reached 100% capacity for the first time on 31 March. The 1100 MWe pressurised water reactor is currently undergoing power ascension testing prior to entering commercial operation.

https://www.world-nuclear-news.org/Articles/Worlds-fourth-Hualong-O...

Construction of Karachi 3, the second of two Hualong One units to be built near Paradise Point in the province of Sindh, began in May 2016. Hot functional testing of Karachi 3 - which simulate the temperatures and pressures that the reactor systems will be subjected to during normal operation and are carried out before loading nuclear fuel - was completed ahead of schedule on 4 November last year. It achieved first criticality on 21 February and was connected to the grid on 4 March.

Various performance and commissioning tests have since been carried out at power levels of 25%, 30%, 50%, 75% and 87% capacity, China National Nuclear Corporation (CNNC) said.

Once testing at full capacity is completed, Karachi 3 will perform a 100-hour demonstration run, after which it will enter commercial operation.

Karachi 2 entered commercial operation in May last year. The units are the first exports of CNNC's Hualong One, which is also promoted on the international market as HPR1000.

The Karachi site - also sometimes referred to as KANUPP - was home to Pakistan's first nuclear power reactor, Karachi 1 - a small 100 MWe (90 MWe net) Canadian pressurised heavy water reactor which shut down in 2021 after 50 years of operation.

The first domestic demonstration plants of CNNC's Hualong One design are Fuqing 5 and 6, in China's Fujian province. The units entered commercial operation in January 2021 and March this year, respectively.

Nuclear energy currently provides around 8% of Pakistan's energy mix from five reactors: four CNNC-supplied CNP-300 pressurised water reactors at Chashma in Punjab, and Karachi 2. CNNC in 2017 signed a cooperation agreement with the Pakistan Atomic Energy Commission on the construction of a Hualong One as a fifth unit at Chashma.

In February, Nucleoeléctrica Argentina and CNNC signed an engineering, procurement and construction contract for the development of the Atucha 3 nuclear power plant. The plant, to be sited near Lima, about 100 kilometres north west of Argentina's capital, Buenos Aires, will use the Hualong One technology.

Comment by Riaz Haq on November 14, 2022 at 10:10am

New hydel projects to produce over 11,000MW
Will enhance overall hydroelectric power capacity to 20,684MW

https://tribune.com.pk/story/2382074/new-hydel-projects-to-produce-...


ISLAMABAD:
The Water and Power Development Authority (Wapda) is pursuing six hydroelectric power projects that will add 11,241 megawatts of environment-friendly electricity to the existing hydel generation capacity of 9,443MW in the coming years.

Talking to APP, Wapda officials said that at present total installed capacity of 24 hydel power stations of Wapda stood at 9,443MW and the addition of 11,241MW would enhance it to 20,684MW.

The existing hydel power stations included Tarbela, Mangla, Ghazi Barotha, Neelum-Jhelum and Warsak, which contributed about 25% to the total system capacity of 36,166MW from all sources.

The net electricity output of those power stations was about 32,000 gigawatt-hours (GWh) per annum.

Sharing details of the upcoming hydel power projects, the officials said that the Dasu Hydropower Project would contribute 4,320MW, Tarbela 5th Extension 1,510MW, Mohmand Dam 800MW, Diamer-Bhasha Dam 4,500MW, Keyal Khwar Power Project 128MW and Kurram Tangi 83.4MW to the national grid system.

Meanwhile, Pakistan Atomic Energy Commission has developed several nuclear power projects to support economic uplift in Pakistan.

Total installed capacity of the nuclear power plants connected with the national grid was 3,530MW, which included 1,330MW Chashma nuclear power project and 2,200MW Karachi nuclear power project.

Comment by Riaz Haq on December 13, 2022 at 5:55pm

Scientists Achieve Nuclear Fusion Breakthrough With Blast of 192 Lasers
The advancement by Lawrence Livermore National Laboratory researchers will be built on to further develop fusion energy research.

https://www.nytimes.com/2022/12/13/science/nuclear-fusion-energy-br...


If fusion can be deployed on a large scale, it would offer an energy source devoid of the pollution and greenhouse gases caused by the burning of fossil fuels and the dangerous long-lived radioactive waste created by current nuclear power plants, which use the splitting of uranium to produce energy.

Within the sun and stars, fusion continually combines hydrogen atoms into helium, producing sunlight and warmth that bathes the planets. In experimental reactors and laser labs on Earth, fusion lives up to its reputation as a very clean energy source.

There was always a nagging caveat, however. In all of the efforts by scientists to control the unruly power of fusion, their experiments consumed more energy than the fusion reactions generated.

That changed at 1:03 a.m. on Dec. 5 when 192 giant lasers at the laboratory’s National Ignition Facility blasted a small cylinder about the size of a pencil eraser that contained a frozen nubbin of hydrogen encased in diamond.

The laser beams entered at the top and bottom of the cylinder, vaporizing it. That generated an inward onslaught of X-rays that compresses a BB-size fuel pellet of deuterium and tritium, the heavier forms of hydrogen.

In a brief moment lasting less than 100 trillionths of a second, 2.05 megajoules of energy — roughly the equivalent of a pound of TNT — bombarded the hydrogen pellet. Out flowed a flood of neutron particles — the product of fusion — which carried about 3 megajoules of energy, a factor of 1.5 in energy gain.

This crossed the threshold that laser fusion scientists call ignition, the dividing line where the energy generated by fusion equals the energy of the incoming lasers that start the reaction.

“You see one diagnostic and you think maybe that’s not real and then you start to see more and more diagnostics rolling in, pointing to the same thing,” said Annie Kritcher, a physicist at Livermore who described reviewing the data after the experiment. “It’s a great feeling.”

The successful experiment finally delivers the ignition goal that was promised when construction of the National Ignition Facility started in 1997. When operations began in 2009, however, the facility hardly generated any fusion at all, an embarrassing disappointment after a $3.5 billion investment from the federal government.


----------

In an interview, Mark Herrmann, program director for weapons physics and design at the Livermore, said the researchers then performed a series of experiments to better understand the surprising August success, and they worked to bump up the energy of lasers by almost 10 percent and improve the design of the hydrogen targets.

The first laser shot at 2.05 megajoules was performed in September, and that first try produced 1.2 megajoules of fusion energy. Moreover, analysis showed that the spherical pellet of hydrogen was not squeezed evenly, and some of the hydrogen essentially squirted out the side and did not reach fusion temperatures.

The scientists made some adjustments that they believed would work better.

“The prediction ahead of the shot was that it could go up a factor of two,” Dr. Herrmann said. “In fact, it went up a little more than that.”

The main purpose of the National Ignition Facility is to conduct experiments to help the United States maintain its nuclear weapons. That makes the immediate implications for producing energy tentative.

Fusion would be essentially an emissions-free source of power, and it would help reduce the need for power plants burning coal and natural gas, which pump billions of tons of planet-warming carbon dioxide into the atmosphere each year.

But it will take quite a while before fusion becomes available on a widespread, practical scale, if ever.

Comment by Riaz Haq on December 27, 2022 at 10:24am

Green investment on rise, Pakistan to get 30 % renewable energy - Pakistan Observer

https://pakobserver.net/green-investment-on-rise-pakistan-to-get-30...


Until now, renewable energy sources make up a very minor fraction of Pakistan’s overall power generation mix. According to a recent report of the National Electric Power Regulatovry Authority, the installed capacity for wind and solar accounts for roughly 4.2% (1,831 MW) and 1.4% (630 MW) of a total of 43,775 MW, respectively.

China is already the biggest investor in green energy in Pakistan. Currently, out of the $144 million in foreign investment in solar PV plants in Pakistan, $125 million is from China, accounting for nearly 87% of the total.

Thanks to Chinese investments, a few weeks ago Federal Power Minister Khurram Dastgir Khan inaugurated two new wind energy projects in Jhimpir, Thatta District, Sindh, with an aim to produce cheaper and clean electricity through indigenous energy sources. Wind projects in this region have been one of several renewable energy projects to have received Chinese investment in recent years. Around 90 kilometers from Karachi, Jhimpir is the heartland of the country’s largest ‘Wind corridor’, which has the potential to produce 11,000 megawatts (MW) of energy from green resources.

Comment

You need to be a member of PakAlumni Worldwide: The Global Social Network to add comments!

Join PakAlumni Worldwide: The Global Social Network

Pre-Paid Legal


Twitter Feed

    follow me on Twitter

    Sponsored Links

    South Asia Investor Review
    Investor Information Blog

    Haq's Musings
    Riaz Haq's Current Affairs Blog

    Please Bookmark This Page!




    Blog Posts

    Pakistani Student Enrollment in US Universities Hits All Time High

    Pakistani student enrollment in America's institutions of higher learning rose 16% last year, outpacing the record 12% growth in the number of international students hosted by the country. This puts Pakistan among eight sources in the top 20 countries with the largest increases in US enrollment. India saw the biggest increase at 35%, followed by Ghana 32%, Bangladesh and…

    Continue

    Posted by Riaz Haq on April 1, 2024 at 5:00pm

    Agriculture, Caste, Religion and Happiness in South Asia

    Pakistan's agriculture sector GDP grew at a rate of 5.2% in the October-December 2023 quarter, according to the government figures. This is a rare bright spot in the overall national economy that showed just 1% growth during the quarter. Strong performance of the farm sector gives the much needed boost for about …

    Continue

    Posted by Riaz Haq on March 29, 2024 at 8:00pm

    © 2024   Created by Riaz Haq.   Powered by

    Badges  |  Report an Issue  |  Terms of Service