Actual vs Potential Hydropower in South Asia. Source: Economist Mag... |
CPEC Suki Kinari project nears completion | The Manila Times
https://www.manilatimes.net/2023/06/12/business/foreign-business/cp...
The Suki Kinari Hydropower project in northwest Pakistan achieved the hoisting of a core component on Saturday, as a 413-ton rotor, crucial to turning water into electricity, was smoothly installed on the last of four generating units.
The successful hoisting of the last rotor will help advance the construction progress of the power station under the China-Pakistan Economic Corridor (CPEC), located in the Mansehra district of the South Asian country's Khyber Pakhtunkhwa province.
Noting the hoisting of the last rotor as a key milestone of the 884-megawatt hydropower project, Yu Zhiliang, assistant general manager of the Suki Kinari Hydropower project of the Overseas Investment Co. of China Gezhouba Group, which invests in and implements the project, said that it marks the installation of the unit body of the hydropower station is coming to an end.
It is also a solid step for the waterless commissioning of four generating units in the coming six months, said Yu.
The hydropower project started construction in January 2017. Once getting functional, the CPEC project will annually generate some 3.21 billion kilowatt-hours of clean electricity, replacing 1.28 million tons of coal and reducing 2.52 million tons of carbon dioxide emissions per year, said Yu.
It will significantly optimize Pakistan's energy structure, boosting the country's economic and social development, he added.
Launched in 2013, the CPEC is a corridor linking Pakistan's Gwadar port with Kashgar in northwest China's Xinjiang Uygur Autonomous Region, highlighting energy, transport and industrial cooperation.
Pakistan will add up to 10 GW of new hydropower capacity by 2030 | Enerdata
https://www.enerdata.net/publications/daily-energy-news/pakistan-wi...
In July 2022, Pakistan commissioned the 720 MW Karot hydropower plant, one of five projects on the Jhelum River (northern Pakistan), alongside the Azad Pattan plant (700 MW), the Mangla Dam (1.1 GW), the Neelum-Jehlum plant (969 MW) and the Kohala plant (1.1 GW).
----------
700MW Azad Pattan hydropower project ready for construction: Energy China - Profit by Pakistan Today
https://profit.pakistantoday.com.pk/2023/06/14/700mw-azad-pattan-hy...
Wang Huihua, Managing Director of China Energy Int’l Group’s Pakistan Branch, announced that the 700-megawatt Azad Pattan hydropower project, run by Energy China, is ready for construction after the completion of a feasibility study and land acquisition.
Wang made these remarks at the ‘Pakistan Energy Sector Landscape: Challenges & Opportunities’ conference held at NUST University, Islamabad.
He explained that the project would provide cheap, clean energy to Pakistan. “We have been developing this project for six years. We hope the government will give it more priority in the China-Pakistan Economic Corridor (CPEC) initiative to expedite financial closure,” he said.
He further stated that Energy China believed that investing in renewable energy in Pakistan was financially viable. “We are committed to setting up our long-term operation in Pakistan and investing more,” he said.
He highlighted that China Energy Engineering Corp. (Energy China) has been present in Pakistan for the past 20 years. “Energy China considers Pakistan as its favored investment destination,” he added.
Wang also pointed out some of the challenges faced by foreign investors in Pakistan, underscoring the importance of resolving them quickly to foster win-win cooperation.
Dasu Hydropower Project: Stage 1 of concrete Starter Dam completed
https://www.nation.com.pk/22-Jun-2023/dasu-hydropower-project-stage...
In a major development towards implementation of Dasu Hydropower Project, Stage 1 of the concrete Starter Dam has been completed upstream of Main Dam site.
As per the design, the Starter Dam for Dasu Hydropower Project is to be completed in two stages; Stage 1 up to elevation of 785 meters while Stage 2 up to elevation of 798 meters above mean sea level, said a spokesperson WAPDA here. The Stage 1 of the concrete Starter Dam was completed in June this year before the high flow season – a major landmark which the project team successfully achieved, the spokesperson said.
As the high flow season has started, River Indus is flowing through the two diversion tunnels completed earlier this year, while some of the river water is overtopping the concrete Starter Dam as designed.
After the high flow season in October this year, the construction of the Starter Dam’s Stage 2 will be carried out. The Stage 2 is scheduled for completion during the coming low flow season. The project is being constructed across the River Indus, upstream of Dasu Town in Upper Kohistan district of Khyber Pakhtunkhwa. The 4,320-MW-Dasu Hydropower Project is planned to be completed in two stages. At present, WAPDA is constructing its stage-I with installed generation capacity of 2,160-MW and annual energy generation of 12 billion units. Stage-I of the project is likely to start electricity generation in 2026. The 2,160-MW stage-II, when implemented, will also provide 9 billion units to the national grid. On completion of the both stages, Dasu will become the project with highest annual energy generation in Pakistan i.e. 21 billion units per annum on the average. The project will commence by end 2026. It is worth mentioning here that in February this year, Dasu Hydropower Project crossed a major milestone as the River Indus was successfully diverted following completion of a 1.33-kilometre long diversion tunnel.
Following the completion of one of the two diversion tunnels, the River Indus was successfully diverted to the completed tunnel. Instead of its natural course, the River Indus is now flowing through a 1.33-kilometer long diversion tunnel with 20-metre width and 23-metre height. Consequently, construction activities have been initiated on the starter dam, leading towards construction of the main dam of Dasu Hydropower Project.
Comment
South Asia Investor Review
Investor Information Blog
Haq's Musings
Riaz Haq's Current Affairs Blog
Samsung is seeing strong demand for its locally assembled Galaxy S24 smartphones and tablets in Pakistan, according to Bloomberg. The company said it is struggling to meet demand. Pakistan’s mobile phone industry produced 21 million handsets while its smartphone imports surged over 100% in the last fiscal year, according to …
ContinuePosted by Riaz Haq on April 26, 2024 at 7:09pm
Pakistani student enrollment in America's institutions of higher learning rose 16% last year, outpacing the record 12% growth in the number of international students hosted by the country. This puts Pakistan among eight sources in the top 20 countries with the largest increases in US enrollment. India saw the biggest increase at 35%, followed by Ghana 32%, Bangladesh and…
ContinuePosted by Riaz Haq on April 1, 2024 at 5:00pm